The 4-Phase Design-Build Process for a Colorado Custom Home

By Yaron, Unison Builds — Colorado-based residential design-build firm Last updated: August 2026
Building a custom home in Colorado through the design-build method moves through four phases: design development, permitting, construction, and final punch list and move-in. Unlike hiring a separate architect and contractor, design-build keeps one team accountable from the first soils report to the day you get your keys — which matters in Colorado specifically, because the site work, engineering, and permitting requirements here are more involved than in most states.
This guide breaks down exactly what happens in each phase, what gets tested and engineered before a single wall goes up, and how long the full process typically takes.
Phase 1: Design Development
This is the longest and most technical phase of a Colorado custom home build, and it’s where most of the site-specific work happens — the work that determines whether your design is actually buildable on your lot before you’re committed to it. Depending on your site, Phase 1 can include all of the following:
Soils report. A geotechnical engineer evaluates soil bearing capacity, expansive soil risk, and groundwater conditions. Colorado has some of the most expansive, moisture-reactive soils in the country in certain regions, and foundation design depends directly on these results.
Survey. A licensed land surveyor establishes property boundaries, easements, and topography — required before architectural or civil design can begin, and often required by the county before permit submission.
Architectural drawings. Full architectural design, from schematic floor plans through construction documents.
Structural engineering. Structural drawings sized for Colorado’s snow-load and seismic requirements, which vary by jurisdiction since Colorado is a home-rule state for building code adoption.
Hazardous material testing (if the project is a scrape/rebuild). If an existing structure is being demolished, testing for asbestos and other hazardous materials is typically required before demolition permits are issued.
Erosion, sediment, and drainage control planning (county-dependent). Many Colorado counties require an ESC (erosion and sediment control) plan and a drainage plan before issuing a grading or building permit — requirements and thresholds vary significantly by jurisdiction, so this is confirmed early with the local building department.
HOA review (if applicable). If the lot is within an HOA, design plans typically require architectural review board approval — a separate timeline from county permitting that needs to be planned for.
Interior design. Material, fixture, and finish selections, ideally locked in during design rather than mid-construction, since late selections are the most common source of schedule delays.
Heat and energy calculations. Manual J/D-style heat loss and gain calculations size the home’s HVAC system correctly for Colorado’s elevation and temperature swings — undersized or oversized systems are a common problem when this step is skipped or rushed.
Electrical load calculations. Engineering to size electrical service and panel capacity correctly for the home’s full design, including any future EV charging or major appliance loads.
Septic engineering (if not on public sewer). For homes not served by a municipal sewer connection, an engineered onsite wastewater treatment system (OWTS) design is required under Colorado’s Regulation 43, with permitting handled by the local county health department.
Water rights (if applicable). For properties relying on a well or requiring augmentation, water rights and well permitting are administered by the Colorado Division of Water Resources — this can be one of the longer lead-time items on a rural or mountain property and is worth investigating early in design, not after.
Design development typically runs 3 to 6 months, with rural and mountain properties trending toward the longer end due to septic, well, and water rights work that urban infill lots don’t require.

Phase 2: Permitting
With design development complete, plans move to the local building department for review and permit issuance. Colorado permitting happens at the county level, so requirements and timelines vary meaningfully by jurisdiction — for example, Jefferson County’s building department outlines its own process for new single-family construction, and a mountain-resort county with an architectural review board will typically add its own review timeline on top of standard plan review.
A design-build team with existing relationships at your specific county building department can meaningfully shorten this phase — this is one of the more overlooked advantages of hiring locally experienced builders over out-of-area firms. Permitting typically takes 4 to 10+ weeks.

Phase 3: Construction
Construction is sequenced deliberately around Colorado’s climate. A typical build order:
- Site work and foundation — excavation, grading, utility connections, foundation pour
- Framing — getting the home weathertight before winter where possible, since exterior work can pause during hard freezes at elevation
- MEP rough-in — mechanical, electrical, and plumbing systems installed per the Phase 1 engineering
- Insulation and drywall
- Interior finishes — flooring, cabinetry, fixtures, paint, using the selections locked in during design
- Exterior finishes and landscaping
NAHB survey data on single-family homebuilding found custom homes averaged roughly 13 months from permit to completion nationally, and Colorado projects generally fall within that range, with complex mountain builds trending longer. Construction is typically the longest phase, running 10 to 18 months depending on size and complexity.

Phase 4: Punch List and Move-In
Before handoff, the design-build team walks the completed home with you to identify and resolve any punch-list items, and provides documentation for systems, warranties, and maintenance schedules. Because one team held the contract for design and construction, there’s a single point of accountability for anything that needs adjusting after move-in — rather than a builder and an architect pointing at each other.
How Long Does the Whole Process Take?
Adding up all four phases, most Colorado custom homes take 12 to 24 months from the start of design development to move-in: roughly 3-6 months for design development, 4-10 weeks for permitting, and 10-18 months for construction, with punch list wrapped into the final weeks of construction. Mountain-county properties with septic, well, and water rights work tend to land toward the longer end of that range. For a full cost breakdown alongside this timeline, see our guide to what it costs to build a custom home in Colorado.
Frequently Asked Questions
What’s included in the design development phase of a custom home build? Design development typically includes a soils report, survey, architectural and structural drawings, heat/energy and electrical load calculations, interior design selections, and — depending on the site — septic engineering, water rights work, HOA review, hazardous material testing for a scrape/rebuild, and an erosion/sediment/drainage control plan.
Do all Colorado custom homes need a septic system and water rights work? No — only properties not connected to a municipal sewer or water system. Homes on public utilities skip septic engineering and water rights work entirely, which can meaningfully shorten the design development phase.
Why does permitting take longer in some Colorado counties than others? Colorado permitting is handled at the county level, and some jurisdictions — particularly mountain resort counties — add architectural review board approval on top of standard building permits, extending the timeline.
What’s the difference between design-build and hiring an architect and contractor separately? In design-build, one company holds a single contract for both design and construction, so pricing and constructability are checked throughout design. With separate architect and contractor relationships, the design is typically finished first, then sent out to bid — which can surface budget problems late in the process. Design-build is now the fastest-growing and most commonly used project delivery method in the United States, according to the Design-Build Institute of America.
How long does the entire process take, from first design meeting to move-in? Most Colorado custom homes take 12 to 24 months total, though rural and mountain properties requiring septic, well, and water rights work often trend toward the longer end.